| Project Name |
Weather Redesign |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
| Fox Project Manager |
Arathi Subramanian |
212-901-4628 |
arathi.subramanian@foxnews.com |
|
|
|
|
|
|
|
In Progress |
RED |
|
| Coban Manager |
Hans Akesson |
|
hans.akesson@cobancorporation.com |
|
|
|
|
|
|
|
Complete |
YELLOW |
|
| OffShore Manager |
|
|
|
|
|
|
|
|
|
|
Cancelled |
GREEN |
|
| Product Manager |
Ted Huang |
|
|
|
|
|
|
|
|
|
On Hold |
TBD |
|
| Business Analyst |
Jennifer McNelis |
|
|
|
|
|
|
|
|
|
Not yet started |
|
|
| Tech Lead |
|
|
|
|
|
|
|
|
|
|
|
|
|
| QA Lead |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
| |
|
TARGET DATE |
STATUS |
DESCRIPTION |
|
|
|
|
|
|
|
|
|
|
| Project Kick-Off |
09/15/09 |
YELLOW |
Not yet started |
|
|
|
|
|
|
|
|
|
|
| Requirement Complete |
09/18/09 |
GREEN |
Not yet started |
|
|
|
|
|
|
|
|
|
|
Dev Cycle Dates (Start - End) |
09/19-10/1 |
GREEN |
Not yet started |
|
|
|
|
|
|
|
|
|
|
| Milestone 1: Component 1 dev complete/demo |
09/22/09 |
GREEN |
Not yet started |
|
|
|
|
|
|
|
|
|
|
| Milestone 2: Component 2 dev complete/demo |
09/29/09 |
GREEN |
Not yet started |
|
|
|
|
|
|
|
|
|
|
| Milestone 3: Component 3 dev complete/demo |
10/01/09 |
GREEN |
Not yet started |
|
|
|
|
|
|
|
|
|
|
| QA |
10/2-10/13 |
GREEN |
Not yet started |
|
|
|
|
|
|
|
|
|
|
| Web Release Date |
10/14/09 |
GREEN |
Not yet started |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|