| #REF! |
|
|
|
|
|
|
| Risk ID |
Summary |
Priority |
Status |
Probability |
Description |
Action Taken |
|
|
|
|
|
|
| |
|
Low, Medium, High |
Active, Resolved, Canceled |
Low, Medium, High |
|
|
|
|
|
|
|
|
| 1 |
Tight Timeline |
High |
Active |
High |
-It has been mandated that we launch the project on March 31. Essentially, that leaves 5 weeks for development, 1 week for QA and performance testing, and we are limited to 2000 VPS hours. |
-Teams have to be flexible and may have to work nights/ weekends in order to meet the deadline. -VPS and FOX have added additional VPS resources. -Some requirements may need to be cut |
|
|
|
|
|
|
| 2 |
Hard Target Date |
High |
Active |
High |
It has been mandated that we launch the project on March 31. Launch date was determined before requirements were finalized and technical analysis was performed. |
-Team have to be flexible and may have to work nights/ weekends in order to meet the deadline. -VPS and FOX have added additional VPS resources. -Some requirements may need to be cut |
|
|
|
|
|
|
| 3 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/21 |
|
|
|
|
|
|
| 4 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/22 |
|
|
|
|
|
|
| 5 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/23 |
|
|
|
|
|
|
| 6 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/24 |
|
|
|
|
|
|
| 7 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/25 |
|
|
|
|
|
|
| 8 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/26 |
|
|
|
|
|
|
| 9 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/27 |
|
|
|
|
|
|
| 10 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/28 |
|
|
|
|
|
|
| 11 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/29 |
|
|
|
|
|
|
| 12 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/30 |
|
|
|
|
|
|
| 13 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/31 |
|
|
|
|
|
|
| 14 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/32 |
|
|
|
|
|
|
| 15 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/33 |
|
|
|
|
|
|
| 16 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/34 |
|
|
|
|
|
|
| 17 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/35 |
|
|
|
|
|
|
| 18 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/36 |
|
|
|
|
|
|
| 19 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/37 |
|
|
|
|
|
|
| 20 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/38 |
|
|
|
|
|
|
| 21 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/39 |
|
|
|
|
|
|
| 22 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/40 |
|
|
|
|
|
|
| 23 |
Hardware/ Software Needs |
High |
Active |
High |
-Purchasing hardware and software necessary for the project is a long process because of all the approvals necessary from Finance. Development hardware will not arrive onsite until 2/18, therefore installation of the development servers will not start unt |
-VPS will have one resource dedicated to setting up the environments. - Local development can continue, before live development environment is fully setup - SAN should be approved by finance on 2/41 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
Low |
Active |
|
| |
|
|
|
|
|
|
|
|
|
Med |
Resolved |
|
| |
|
|
|
|
|
|
|
|
|
High |
Cancelled |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|